Procurement Delays and Project Outcomes in Cameroon's Airport Sector
DOI:
https://doi.org/10.63671/ijsesr.v2i3.154Keywords:
procurement delays, project outcomes, airport infrastructure, public procurement reform, Cameroon, MINMAP, project managementAbstract
Public infrastructure delivery in sub-Saharan Africa is repeatedly undermined by delays that originate not on the construction site but in the procurement process that precedes it. This article examines the relationship between procurement delays and project outcomes in Cameroon's airport sector, drawing on documentary evidence from the Transport Sector Development Project (PDST), the ongoing modernisation of Douala International Airport, and the regulatory reform of Cameroon's public contracts system. The study is framed by transaction cost economics, principal-agent theory, and the time-cost-quality model of project success, and it employs a qualitative, case-based documentary design that triangulates World Bank implementation reports, government procurement guidance, and industry news coverage. Findings indicate that procurement delays in Cameroon's airport sector are driven primarily by fragmented institutional responsibility between the Ministry of Public Contracts (MINMAP) and the procurement regulatory authority, protracted contractor disputes and cancelled awards, slow disbursement and counterpart-funding bottlenecks, compliance requirements imposed by the International Civil Aviation Organization, and, until recently, a heavy reliance on paper-based tendering. These delays translate into schedule slippage of several years beyond appraisal targets, cost escalation, deferred safety and security certification, and diminished stakeholder confidence. The article concludes that digitalisation of procurement through the Cameroon Online E-Procurement System, clearer division of authority between MINMAP and the regulator, and stronger front-end project preparation are central to improving airport project outcomes, and it offers recommendations for policy and practice accordingly.
References
African Development Bank Group. (2026, July). AfDB approves CFA833.8 billion in new financing for Cameroon since 2023 [News release]. fundsforNGOs News. https://news.fundsforngos.org/2026/07/20/african-development-bank-approves-cfa833-8-billion-in-new-financing-for-cameroon-since-2023/
Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349–357.
Business in Cameroon. (2021, November 12). Cameroon: Public procurement regulatory agency ARMP lists corrupt practices in the sector. https://www.businessincameroon.com/economy/1211-12050-cameroon-public-procurement-regulatory-agency-armp-lists-corrupt-practices-in-the-sector
Business in Cameroon. (2026, January 21). Cameroon targets June 2026 to finish CFA30.4bn airport security upgrades. https://www.businessincameroon.com/public-management/2101-15634-cameroon-targets-june-2026-to-finish-cfa30-4bn-airport-security-upgrades
Cameroon Public Procurement Authority. (n.d.). About us. https://cameroonppa.com/about-us/
Cameroon-Concord News. (2024, November 22). Cameroon's airport infrastructure: Aéroports du Cameroun responds to criticism, announces renovations. https://www.cameroon-concord.com/business/cameroons-airport-infrastructure-aeroports-du-cameroun-responds-to-criticism-announces-renovations
Ecofin Agency. (2026). Cameroon unveils final design for Douala airport upgrade ahead of 2026 start. https://www.ecofinagency.com/news-infrastructures/1411-50513-cameroon-unveils-final-design-for-douala-airport-upgrade-ahead-of-2026-start
Formation Marches Public. (2024). Public procurement reglementation [Training course]. Republic of Cameroon. https://formation-marchespublic.cm/course/view.php?id=6
Frimpong, Y., Oluwoye, J., & Crawford, L. (2003). Causes of delay and cost overruns in construction of groundwater projects in a developing country: Ghana as a case study. International Journal of Project Management, 21(5), 321–326.
Jensen, M. C., & Meckling, W. H. (1976). Theory of the firm: Managerial behavior, agency costs and ownership structure. Journal of Financial Economics, 3(4), 305–360.
Kaliba, C., Muya, M., & Mumba, K. (2009). Cost escalation and schedule delays in road construction projects in Zambia. International Journal of Project Management, 27(5), 522–531.
Ministry of Public Contracts. (2025, March). Public contracts regulation guide. Republic of Cameroon. https://minmap.cm/wp-content/uploads/2025/05/GUIDE_FINAL_REGULATION-_ENG_2025.pdf
Nkafu Policy Institute. (2022, May 9). Infrastructure development policy and sustainable, inclusive growth in Cameroon. https://nkafu.org/infrastructure-development-policy-and-sustainable-inclusive-growth-in-cameroon/
Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK Guide) (7th ed.).
Public Contract Regulatory Agency. (2024, July 28). SAGO 2024: Public Contract Regulatory Agency stages conspicuous presence. The Guardian Post. https://theguardianpostcameroon.com/post/3597/fr/sago-2024-public-contract-regulatory-agency-stages-conspicuous
Republic of Cameroon. (2018). Decree No. 2018/366 of 20 June 2018 to institute the Public Contracts Code.
Republic of Cameroon, Presidency. (n.d.). Public contract regulatory agency (ARMP). https://www.prc.cm/en/the-presidency/49-organisation/attached-services/82-public-contract-regulatory-agency-armp
Tendersgo. (2026, May 5). Cameroon's COLEPS: Zero-tolerance mandatory e-procurement in 2026. https://www.tendersgo.com/post/cameroons-coleps-zero-tolerance-mandatory-e-procurement-2026-3252
U.S. Department of State. (2025). 2025 investment climate statements: Cameroon. https://www.state.gov/reports/2025-investment-climate-statements/cameroon
Williamson, O. E. (1985). The economic institutions of capitalism: Firms, markets, relational contracting. Free Press.
World Bank. (2017, January 17). Cameroon Transport Sector Development Project (P150999): Implementation status and results report, sequence no. 1. https://documents1.worldbank.org/curated/en/445251484665112399/text/ISR-Disclosable-P150999-01-17-2017-1484665101456.txt
World Bank. (2019, July 25). Cameroon Transport Sector Development Project (P150999): Implementation status and results report, sequence no. 5. https://documents1.worldbank.org/curated/en/312841564077021039/text/Disclosable-Version-of-the-ISR-Cameroon-Transport-Sector-Development-Project-P150999-Sequence-No-05.txt
World Bank. (2021, June 10). Cameroon Transport Sector Development Project (P150999): Implementation status and results report, sequence no. 9. https://documents1.worldbank.org/curated/en/694991623343461724/text/Disclosable-Version-of-the-ISR-Cameroon-Transport-Sector-Development-Project-P150999-Sequence-No-09.txt
World Bank. (2024, August 26). Cameroon Transport Sector Development Project (P150999): Procurement plan. https://documents.worldbank.org/en/publication/documentsreports/documentdetail/099082624105032914
World Bank. (2024). Report No. ICR00006650: Implementation completion and results report [Public Financial Management and Statistical Capacity project]. https://documents1.worldbank.org/curated/en/099071024022031798/pdf/BOSIB-72773152-d22e-4d80-b4a6-5965ed9e8b72.pdf
World Economic Forum. (2015, May). How Cameroon is tackling its procurement problems. https://www.weforum.org/stories/2015/05/how-cameroon-is-tackling-its-procurement-problems/
Downloads
Published
Issue
Section
License
Copyright (c) 2026 International Journal of Science and Engineering Science Research

This work is licensed under a Creative Commons Attribution 4.0 International License.